Applications and Compliance

Tactile Paving Requirements for Indian Metro Stations: What DMRC and Other Metro Tenders Ask For

Stainless steel tactile tile with 36 concentric ring studs

Key takeaways

  • Metro tenders usually specify stainless steel tactile tiles or studs at platform edges and guiding paths from entrances to gates, lifts and platforms.
  • Expect a drawing with the stud profile and spacing; confirm it before quoting, because dome shapes differ between operators.
  • SS 316 is commonly called for in coastal cities and open-air stations; SS 304 in enclosed concourses.
  • Samples, mill certificates and a method statement are normally required before the first delivery.

Indian metro corporations write some of the most detailed tactile specifications a contractor will meet. Delhi Metro Rail Corporation (DMRC) drawings have been copied, with changes, by many later systems, so a tender in Pune, Nagpur, Kochi or Patna often reads like a DMRC document with local additions. This article sets out what those specifications usually contain, based on the projects MetalX has supplied, so a contractor knows what to check before pricing.

Where tactile paving is required in a station

  • Platform edge: a continuous warning field along the full length of the platform, normally 600 mm deep, set back from the coping edge or the platform screen door line by a dimension shown on the drawing (often 300 mm to the near edge of the field).
  • Stairs and escalators: warning fields at the top and bottom landings, full width, 600 mm deep.
  • Lifts: a warning square in front of the call button and the lift door.
  • Guiding paths: directional indicators from every entrance through the unpaid area to the ticket counter, automatic fare collection gates, lifts and stairs, and on the paid side to the platform.
  • Entrances and foot-over-bridges: warning fields at the head and foot of external stairs and ramps and at the property line.

What the drawings specify

Most metro drawings show a stud with a stated top diameter, base diameter, height and centre spacing, and a bar with a stated width, length, height and spacing. Some show a domed top with concentric rings; others show a flat-topped truncated cone. The two are not interchangeable in the eyes of a resident engineer, so confirm which profile the drawing shows before you quote. MetalX holds tooling for both, on loose studs and on integrated tiles.

Material clauses

Stainless steel is standard. Tenders in Mumbai, Chennai, Kochi and other coastal cities, and for elevated open-air stations anywhere, generally call for AISI 316. Underground and enclosed stations often accept AISI 304. The specification will ask for mill test certificates traceable to the batch, and sometimes for third-party inspection of a sample lot. Polyurethane or porcelain is occasionally permitted in back-of-house areas or at entrance plazas.

Tiles or studs

Platform edges are almost always integrated tiles: they install quickly in night possessions, align perfectly, and cannot be prised out. Loose studs are used around columns and curved edges, and for guiding-path turns. Some operators specify the tile fixing (screws plus adhesive) and the screw type; others leave it to a method statement.

Submittals you should expect to provide

  1. Physical samples of the tile and stud for approval, usually two of each.
  2. Dimensioned shop drawings showing the layout against the station architectural drawings.
  3. Mill test certificates for the stainless steel.
  4. A method statement covering setting out, fixing, adhesive and protection.
  5. Manufacturer details and, sometimes, evidence of previous metro supply.

MetalX prepares the first four with the contractor and can provide references from Indian and Gulf metro projects, including a Saudi Arabia metro supplied with SS 316 studs.

Common reasons tactile work gets rejected on metro sites

  • Stud profile does not match the drawing (domed instead of truncated, or the reverse).
  • Field not continuous across column bays or at platform ends.
  • Setback from the platform edge measured to the wrong reference line.
  • Grade certificate missing or not traceable.
  • Tiles laid with visible gaps or proud screw heads.

Quantities for a typical station

A two-platform station with 140 m platforms needs about 1,900 platform-edge tiles, plus 200–300 tiles for stair and escalator landings, and several thousand loose studs and bars for lifts, columns and guiding paths. MetalX can produce a bill of quantities from the station drawings and hold the full quantity in stock ahead of the possession programme.

Frequently asked questions

Do Indian metro tenders require SS 316 tactile tiles?

Commonly in coastal cities and for open-air elevated stations; enclosed underground stations often accept SS 304. Check the material clause and the station location.

Can polyurethane tactile indicators be used in a metro station?

Rarely on platforms or concourses, where stainless steel is specified. Some operators allow PU in back-of-house areas or entrance plazas. Confirm with the tender.

What samples are needed before supplying tactile tiles to a metro project?

Usually two physical samples each of the tile and stud, shop drawings, mill test certificates and a method statement. MetalX prepares these with the contractor.

How long does MetalX take to supply a metro order?

Standard tiles and studs ship from stock in Mumbai. Project quantities are manufactured to programme and can be held in stock and released to match night possessions.

About the author. This article was written by the engineering and export team at MetalX Engineering Inc., a Government of India recognised Export House that has manufactured tactile ground surface indicators in Mumbai for over three decades. Product specifications quoted here refer to MetalX standard items; always confirm dimensions against your project specification. More about MetalX →

Related articles

Need tactile indicators for your project?

Send us your drawings, quantities and delivery location. We reply with a quotation, technical datasheet and lead time, usually within one working day.